STATUS UPDATE: Pre-Production 5150

It’s been a busy 2 weeks as  we kicked off pre-production on an 11,000 sq ft Level 5 house. In 2 weeks we primed all the ceilings and walls twice and applied our first coat of finish wall paint on the 2nd, 3rd and 4th floor. The ceilings were painted on the 2nd, 3rd and 4th floors. We taped off, pulled, re-primed and painted 60 casement windows. We also primed the poplar trim package for the 3rd and 4th floor twice with Zinsser Cover Stain oil, sanding between coats. As if that was enough to keep busy, we also primed three other houses. There are many photos of progress on flickr with descriptions. Check it out!

Our last pre-production day is today. The trim carpenters will have their time in the house before we go back to start production.